Romania is becoming one of the more active data centre markets in Central and Eastern Europe. For years the market was small, made up of carrier-neutral colocation sites in Bucharest and enterprise or telecom facilities in Timișoara, Cluj-Napoca and Brașov. A study by Cushman & Wakefield Echinox, cited by the Romanian press in 2026, puts the country at about 63 data centres with a combined capacity of under 100 MW (ClickȘtiri / Cushman & Wakefield Echinox). Since late 2025, however, announced projects have added up to well over a gigawatt of potential capacity, driven by AI compute demand, Romania’s energy mix, land availability and its role as a NATO and EU frontier state.
This article ranks the ten largest verifiable data centre investments and initiatives in Romania. For each it gives the investor, location, capacity, disclosed investment value and status, with links to official or press sources. It then explains the market context: connectivity, power and grid access, renewables and nuclear, EU data centre rules, the EU AI gigafactory initiative, state aid and FDI screening. It ends with risks, an outlook, an FAQ and practical guidance for investors.
How We Built This Ranking
Ranking basis: announced maximum power capacity (MW). We rank by capacity rather than investment value because most projects have not disclosed a total capital cost, so a ranking by value would be incomplete and misleading. Where a project gives both IT load and total facility power, we use the larger published figure for ranking and quote both. Projects with no published capacity are placed at the end and labelled.
Inclusion rule: every project must be named in at least one official statement or credible press or trade source, linked below. We did not estimate any capacity or value. Where a figure was not public, we say “not disclosed”. We could fully verify nine distinct projects with capacity or value data. The tenth entry is the Romanian government cloud, a verified investment with a disclosed budget but no published MW figure. An eleventh item, M247’s Brașov facility, appears in a separate, clearly labelled pipeline section because neither its capacity nor its value is public. Most of the large projects are announced or in development, not built. Status matters as much as size.
Top 10 Data Center Investments in Romania (Ranked by Capacity)
| # | Project | Investor | Location | Capacity | Investment value | Status |
|---|---|---|---|---|---|---|
| 1 | Black Sea AI Gigafactory | Romanian Government (Ministry of Energy, Ministry of Finance, Authority for Romania’s Digitalization) with a consortium leader still to be selected | Cernavodă–Constanța corridor (Phase I), Doicești (Phase II) proposed | Up to 1,500 MW energy mix (2025 bid); EOI: about 20,000 GPUs first phase, scalable to 100,000+ GPUs and 1 GW+ | Up to USD 5 billion (ADR estimate) | Government initiative; EOI for consortium leader launched 2026 |
| 2 | ClusterPower × AIC AI Data Center Region | ClusterPower (RO) and Accelerated Infrastructure Capital | Mischii (MSC1) and Făurești (FRS1), Dolj County | 800 MW total (512 MW Mischii + 300 MW Făurești) | Not disclosed | MSC1 operating (10 MW); phased delivery 2026–2029 |
| 3 | WDP / Lamas Invest twin data centres | WDP Romania and Lamas Invest | Ștefăneștii de Jos, Ilfov (near Bucharest) | 2 × 190 MW = 380 MW (grid consumption approvals) | Not disclosed | Permitting; new 220 kV substation required |
| 4 | Npower Solar Energy data centre (Hagag) | Hagag (acquirer) / Npower Solar Energy | Southern Romania | 120–125 MW IT (168–175 MW total) | EUR 67.5 million (acquisition price for the project company, not construction cost) | Conditional acquisition; ATR and ready-to-build milestones pending |
| 5 | DriverAI Quantum AI Data Center | DriverAI LLC (US), Leviatan Group park | Luna, Cluj County | 80 MW (4 × 20 MW phases) | About USD 1 billion for phase one (as stated by Senate President) | Announced 2026; site evaluation completed |
| 6 | Sany Timiș hybrid energy and data centre | Sany International with Danube Solar Seven | Timișoara (data centre), Uivar (solar) | 70 MW IT | About EUR 350 million for the data centre (of about EUR 1 billion total project) | Announced 2026 (MoU) |
| 7 | M247 Bucharest expansion | M247 Global | Bucharest (Pipera) | From 2 × 2 MW to 7 MW | “Several tens of millions of euros” | Expansion under way; completion about mid-2027 |
| 8 | NXDATA-3 | NXDATA | Tunari, Ilfov (Bucharest Ring Road) | 5 MW total / 3 MW IT | Not disclosed | Opening estimated Q4 2026 |
| 9 | ClusterPower MSC1 (phase one, built) | ClusterPower | Mischii, Dolj County | Designed for up to 200 MW / 4,500 racks; about 10 MW available today | EUR 36–45 million (incl. RON 82 million state aid) | Operating since 2021–2022; base for #2 |
| 10 | Government Cloud (Cloud Guvernamental) | Romanian State; STS as core infrastructure provider | Multiple government sites | Not disclosed | EUR 500 million (PNRR) | In implementation |
1. Black Sea AI Gigafactory — up to 1,500 MW (government initiative)
In June 2025 Romania sent the European Commission a letter of intent to host one of the EU’s planned AI gigafactories. The original concept was more than 100,000 AI accelerators across two sites: Cernavodă (Phase I), with direct nuclear supply and fibre and submarine cable connectivity, and Doicești (Phase II), an industrial site with potential to co-locate with the planned NuScale small modular reactor. The concept was powered by an energy mix of up to 1,500 MW. The Authority for Romania’s Digitalization estimated the investment at up to USD 5 billion (Business Forum; Romania Insider).
In 2026 the Ministry of Energy and the Ministry of Finance, with technical support from ADR, launched an Expression of Interest to pre-select a consortium leader. The EOI asks for an initial deployment of about 20,000 GPUs, scalable to about 100,000 GPUs and 1 GW or more of facility power. It names the Cernavodă–Constanța corridor as a potential location but leaves the final site open (Ministry of Energy – EOI announcement; EOI Clarification Q&A). Status: early stage. There is no selected consortium, final design, financing or EU award yet.
2. ClusterPower × Accelerated Infrastructure Capital — 800 MW AI region (Dolj)
In December 2025, Romanian operator ClusterPower and data centre investor Accelerated Infrastructure Capital (AIC) signed an equity partnership to co-develop an 800 MW AI data centre region in south-western Romania. The existing MSC1 campus in Mischii, near Craiova, has 10 MW available now. The plan is to deliver 70 MW ready-for-service by end-2026, a further 144 MW by end-2027 and 288 MW by end-2028/early 2029, reaching 512 MW. A second campus at Făurești (FRS1), about 30 km away, is planned to add 300 MW from 2029 (DCD). Investment value: not disclosed. Status: MSC1 is operating, and expansion phases are scheduled.
3. WDP / Lamas Invest — 2 × 190 MW at Ștefăneștii de Jos (Ilfov)
WDP Romania, part of the Belgian logistics real estate group, and Lamas Invest, controlled by WDP Romania head Jeroen Biermans, are preparing two data centres near WDP’s industrial park in Ștefăneștii de Jos, just north-east of Bucharest. Each has received approval for 190 MW of consumption, 380 MW in total. Grid connection requires a new 220 kV substation tied to the Fundeni–Brazi Vest overhead line (Libertatea, citing Profit.ro). Investment value: not disclosed. Status: permitting.
4. Npower Solar Energy / Hagag — 120–125 MW IT (southern Romania)
Real estate investor Hagag has agreed to acquire Npower Solar Energy, a company developing a data centre of 120–125 MW IT (about 168–175 MW total) in southern Romania. The transaction is valued at EUR 67.5 million, payable in instalments tied to milestones. It is conditional: grid technical approval (ATR) within four months, ready-to-build status within 12 months, and a signed end customer, failing which the deal lapses (CIJ World, citing Economica.net; ClickȘtiri). The EUR 67.5 million is the acquisition price, not the construction budget.
5. DriverAI — 80 MW “Quantum AI” data centre (Luna, Cluj)
US company DriverAI plans an 80 MW data centre combining high-density GPU infrastructure and quantum computing hardware. It would be built in four 20 MW phases on a 20-hectare site in Leviatan Group’s industrial and technology park in Luna, Cluj County, near Câmpia Turzii (Agenda Construcțiilor; DCD). Romania’s Senate President stated that about USD 1 billion would be invested in the first stage (Digi24). DCD noted that the company itself had not confirmed total project cost. Status: announced, in advanced preparation.
6. Sany Timiș — 70 MW data centre within a EUR 1 billion hybrid energy project
Chinese industrial group Sany, through a Singapore-registered subsidiary and Romanian partner Danube Solar Seven, plans the “Timiș Sany” project. It comprises 2.8 GWp of solar in Uivar, a 2.34 GWh battery storage system and a 70 MW IT data centre in Timișoara, which sits on the fibre route to Frankfurt. Total investment is put at about EUR 1 billion, of which about EUR 350 million is for the data centre (Romania Insider, citing Profit.ro; DCD). Status: memorandum signed. Because the investor is non-EU and the project involves digital and energy infrastructure, it is likely to fall under Romania’s FDI screening regime.
7. M247 Global — Bucharest capacity expansion to 7 MW
M247 Global operates two Bucharest data centres of 2 MW each, including the Pipera facility, which runs on renewable electricity and was at 100% occupancy in 2025. In May 2026 it announced an investment of “several tens of millions of euros” to raise capacity to 7 MW, with 200 high-density racks able to support AI workloads and completion in about a year (Economica.net; Energynomics).
8. NXDATA-3 — 5 MW (Tunari, Ilfov)
NXDATA, which runs the NXDATA-1 and NXDATA-2 carrier-neutral sites (3.23 MVA combined; NXDATA overview), is building NXDATA-3 on the Bucharest Ring Road in Tunari. It has 5 MW of installed power, 3 MW of IT capacity, four data halls on 2,000 m², a design PUE of 1.3 and Tier III-compliant design. Opening is estimated for Q4 2026 (NXDATA-3). Investment value is not disclosed.
9. ClusterPower MSC1 (phase one) — completed hyperscale-ready campus
ClusterPower’s Mischii campus was built in 2020–2021. Its initial investment was reported at RON 172 million (about EUR 36 million), including RON 82 million of state aid from the Ministry of Finance (The Romania Journal). Later reports put phase one at EUR 40 million (DCD) and the built facility at about EUR 45 million (Tema Energy). The campus is designed for up to 4,500 racks and 200 MW, with on-site gas-fired trigeneration, Uptime Tier III certification and a reported PUE of about 1.1. It shows that Romanian state aid has already co-financed a data centre and gives the platform for the AIC expansion.
10. Romanian Government Cloud — EUR 500 million (PNRR)
Romania’s government cloud programme, announced in 2022, is to be financed with EUR 500 million from the National Recovery and Resilience Plan, with the Special Telecommunications Service (STS) providing the core infrastructure (DC Market Insights). No aggregate MW figure has been published, so it ranks last on our capacity basis. By value it is among the largest disclosed. It is relevant to private investors as a source of demand for hardware, connectivity, integration and security services.
Pipeline / Other Announced (Not Ranked)
Listed for completeness only. Capacity and investment value are not publicly disclosed.
- M247 – Euro Data Center (EUDC), Brașov: acquired in April 2026 to form a second, geographically separate M247 region in Romania for disaster recovery. A “multi-million dollar” upgrade has been announced (Economica.net).
Market Context: Why Romania Is on the Data Center Map
A small installed base with a big pipeline
Romania still hosts less than 100 MW of operational capacity across about 63 sites. Bucharest has 28, followed by Timișoara (10), Cluj-Napoca (8) and Brașov (5) (ClickȘtiri). Announced projects add up to more than 1.5 GW. Grid operator Transelectrica expects data centre demand of 370 MW by 2030 and 680 MW by 2035 in its realistic scenario, and 620 MW and 1,080 MW respectively in its optimistic scenario (Libertatea / Transelectrica). The gap between announcements and grid expectations is a useful reminder that not every project will be built.
Bucharest connectivity and regional fibre routes
Bucharest is the country’s main interconnection hub. Carrier-neutral facilities such as NXDATA-1/2 are among the most densely interconnected in South-East Europe (NXDATA). Timișoara sits on the terrestrial data route towards Frankfurt (Romania Insider), and the Constanța region offers subsea cable access, which the government cites as an asset for the Gigafactory (Business Forum). Latency-sensitive workloads still favour Bucharest. Power-hungry AI training workloads can locate in Oltenia, Cluj or Dobrogea, where power and land are available.
Power, grid access and prices
Grid access is the decisive constraint. Since 2025, capacity for projects of 5 MW or more is allocated through a structured process with annual allocation rounds, and holders of a technical connection approval (ATR) must post financial guarantees (Dentons; ICLG). Industry voices argue Romania has enough generation capacity for data centres and that an ATR can be obtained within months when the site and solution study are ready. Permitting and substations, however, take longer (Energynomics). The WDP project needs a new 220 kV substation, and Hagag’s deal depends on getting an ATR, which shows how central the grid is to bankability.
Romanian electricity prices rose after 2021 and remain volatile. Romania’s inflation was driven by energy prices again in 2026 (European Commission). Large consumers typically reduce exposure through long-term PPAs with renewable or nuclear producers, behind-the-meter generation (as with ClusterPower’s gas trigeneration and Sany’s solar-plus-storage design), or co-location with generation.
Renewables, gas and nuclear
Romania’s mix of hydro, nuclear, wind, fast-growing solar and gas is an important selling point. Black Sea gas from Neptun Deep is expected from H1 2027, with about 8 bcm a year at plateau (OMV Petrom). Cernavodă Units 3 and 4 are targeted for 2030–2031 (Nuclearelectrica), and the NuScale SMR project at Doicești is being developed. The government’s Gigafactory concept is explicitly built around this carbon-free nuclear baseload (Romania Insider).
EU rules: Energy Efficiency Directive and the data centre reporting scheme
Under the recast Energy Efficiency Directive (EU) 2023/1791, operators of data centres with installed IT power demand of at least 500 kW must report key performance indicators each year to a European database, including energy consumption, PUE, renewable share, water use and waste heat reuse (Directive (EU) 2023/1791). The detailed reporting scheme is set out in Delegated Regulation (EU) 2024/1364 (EUR-Lex). The directive also requires facilities above 1 MW to use waste heat or other recovery solutions unless this is technically or economically unfeasible. Investors should design for these metrics from day one, as they increasingly feed into permitting, financing (EU Taxonomy alignment) and customer due diligence.
The EU AI gigafactory initiative
In February 2025 the European Commission launched InvestAI, which aims to mobilise EUR 200 billion for AI investment, including a EUR 20 billion fund for AI gigafactories (European Commission). Romania’s Black Sea AI Gigafactory bid is its attempt to secure a share. Selection by the EU would bring EU and EuroHPC co-financing and could anchor a wider ecosystem of suppliers, connectivity and smaller AI facilities.
Incentives and State Aid for Data Centers
Precedent: ClusterPower’s Mischii campus received RON 82 million of Ministry of Finance state aid (The Romania Journal), so data centres have qualified for Romanian regional investment aid before.
HG 486/2026: the Ministry of Finance’s new scheme (grant or tax credit, minimum eligible investment RON 50 million, about EUR 150 million average annual budget, agreements until 2032) targets manufacturing sectors where Romania has a trade deficit (HG 486/2026; Ministry of Finance). Data centre operations are classified as IT services, not manufacturing, so do not assume they are eligible. Check the list of eligible activity codes in Annex 1 before relying on it. Equipment manufacturers serving data centres (electrical equipment, cooling, modular buildings) may qualify.
GEO 8/2026 created a framework for large state aid schemes for strategic investments, R&D, net-zero technologies and innovation, using enhanced depreciation and multi-year tax credits (KPMG). Implementing schemes could be relevant to large AI and compute projects. Other options include EU GBER regional aid and R&D aid (Regulation (EU) 651/2014), EU-funded digital programmes, local property tax relief and industrial park benefits. Incentive rules require applications before work starts.
FDI Screening for Non-EU Investors
Digital infrastructure, data processing and storage, and energy are among the sensitive sectors under Romania’s FDI screening law, GEO 46/2022. Since 13 March 2026, non-EU investments in these fields above EUR 5 million must be notified to the CEISD and approved before closing. Smaller deals can still be reviewed, investments made within one year are aggregated, and some asset deals (land, infrastructure, IP) are caught (GEO 46/2022; Dentons). Almost any large data centre deal by a US, Israeli, Chinese, Gulf or other non-EU investor should therefore include CEISD clearance in its timetable. Expect questions on ultimate beneficial owners, sources of funds and data security.
Risks to Consider
- Announcement risk: most of the capacity on this list is announced, not built. Several deals are conditional (Hagag) or still at MoU or EOI stage (Sany, Gigafactory). Underwrite only what has an ATR, permits, land and customers.
- Grid and substation timelines: new 110/220/400 kV connections and substations can take years and need large guarantees.
- Power price volatility: without long-term PPAs or on-site generation, energy costs can wipe out margins.
- Permitting and bureaucracy: zoning, environmental, water and construction permits vary by county and can be slow.
- Skills: experienced data centre engineers and facility staff are scarce outside Bucharest. Eurostat shows labour costs rising quickly, though still low at EUR 13.6/hour in 2025 (Eurostat).
- Regulatory: EED reporting and waste heat obligations, FDI screening, and possible future data sovereignty rules for public sector workloads.
- Macro and fiscal: Romania’s high deficit and slow 2026 growth may affect public co-financing and tax stability (European Commission).
- Demand concentration: large AI campuses depend on a handful of hyperscale or AI tenants, so pre-leasing is essential.
Outlook
If even part of the pipeline is delivered, Romania’s data centre capacity could grow several-fold by the end of the decade, in line with Transelectrica’s projections of 370–620 MW by 2030. The most likely early winners are projects that already control power: ClusterPower/AIC in Oltenia, with on-site generation and an operating campus, and Bucharest colocation expansions such as M247 and NXDATA-3. The 2027 milestones are worth watching: Neptun Deep gas, the Cernavodă 3 and 4 investment decision, ClusterPower’s 144 MW phase and the Gigafactory consortium selection. Large greenfield hyperscale projects near Bucharest (WDP) and in the west (Sany) will depend on substations, tenants and, for non-EU investors, FDI clearance.
How to Invest: A Practical Checklist
- Secure land with zoning suitable for data centres, close to a transmission substation and fibre routes.
- Apply early for grid capacity (ATR) and budget for guarantees.
- Structure power supply: PPAs, on-site generation or storage, or co-location with renewables or nuclear.
- Screen FDI exposure (GEO 46/2022) and merger control at term-sheet stage.
- Map incentives (GBER regional aid, GEO 8/2026 schemes, EU funds) and file before works start.
- Design for EED KPIs: PUE, renewable share, water use and waste heat reuse.
- Line up anchor tenants and financing (project finance, infrastructure funds, EU/EIB instruments).
Frequently Asked Questions
What is the largest data center project in Romania?
By announced capacity, the government-led Black Sea AI Gigafactory (up to 1,500 MW in the 2025 concept) is the largest initiative, followed by the private ClusterPower × AIC 800 MW AI region in Dolj. Neither is fully built.
How much data center capacity does Romania have today?
Less than 100 MW across about 63 facilities, according to Cushman & Wakefield Echinox data cited in 2026.
Where are Romanian data centers located?
Mostly in Bucharest and Ilfov, then Timișoara, Cluj-Napoca and Brașov. New AI-scale campuses are planned in Dolj (Craiova area), Cluj County, Timiș and the Cernavodă–Constanța corridor.
Do data centers qualify for state aid in Romania?
They have before: ClusterPower received RON 82 million. The new HG 486/2026 scheme targets manufacturing, so data centre eligibility is not assured. GBER regional aid and future GEO 8/2026 schemes are other routes.
Do non-EU investors need approval?
Usually yes for investments above EUR 5 million in digital or energy infrastructure. CEISD clearance under GEO 46/2022 is needed before closing.
What EU rules apply?
The Energy Efficiency Directive (EU) 2023/1791 requires annual KPI reporting for data centres of 500 kW or more and waste heat assessment above 1 MW, under Delegated Regulation (EU) 2024/1364.
Is Romania part of the EU AI gigafactory programme?
Romania has bid for the Black Sea AI Gigafactory under the EU’s InvestAI initiative, and in 2026 launched an EOI to select a consortium leader. No EU award had been announced at the time of writing.
How long does a grid connection take?
It varies. An ATR can be issued within months for well-prepared sites, but building new high-voltage substations can take several years.
Conclusion
Romania offers data centre investors several advantages: a low-carbon energy mix with new gas and nuclear on the way, available land, EU and NATO membership, competitive costs and a fast-growing AI project pipeline. It is also a market where power, permits and tenants decide which announcements become operating megawatts. Investors who secure grid capacity, energy supply, incentives and regulatory clearances early will be best placed.
LEW assists data center investors in Romania with site identification, grid and permitting strategy, project funding, and state aid and EU incentive applications. Fees are available on request. Call +40 21 310 27 01 to discuss your project.
This article is for general information only and is not investment, legal or tax advice. Project data reflect public sources as of October 2026. Announced projects may change, be delayed or be cancelled.
Sources
- DCD – AIC partners with ClusterPower on 800MW build-out
- Romania Insider – Sany EUR 1bn green energy and data centre project
- DCD – Sany International data center in Timișoara
- DCD – DriverAI 80MW quantum AI data center in Cluj
- Digi24 – DriverAI project in Cluj
- Agenda Construcțiilor – DriverAI and Leviatan
- CIJ World – Hagag acquires largest data center project
- ClickȘtiri – Hagag / Cushman & Wakefield market data
- Libertatea – WDP 2 × 190 MW data centres near Bucharest
- Business Forum – Romania submits bid for Black Sea AI Gigafactory
- Romania Insider – Gigafactory and nuclear power
- Ministry of Energy – Black Sea AI Gigafactory EOI
- Ministry of Energy – EOI Clarification Q&A
- The Romania Journal – ClusterPower construction and state aid
- DCD – ClusterPower breaks ground
- Tema Energy – ClusterPower case study
- Economica.net – M247 Bucharest expansion
- Energynomics – M247 green energy data centers
- NXDATA-3 official site
- NXDATA overview
- DC Market Insights – Romania data center infrastructure market
- Energynomics – Romania power capacity for data centers
- Dentons – Grid capacity allocation for projects ≥ 5 MW
- ICLG – Securing access to the electricity grid in Romania 2026
- Directive (EU) 2023/1791 (Energy Efficiency Directive)
- Delegated Regulation (EU) 2024/1364
- European Commission – InvestAI and AI gigafactories
- HG 486/2026 text
- Ministry of Finance – HG 486/2026
- KPMG – GEO 8/2026
- Regulation (EU) 651/2014 (GBER)
- GEO 46/2022 consolidated text
- Dentons – Romania FDI screening amended 2026
- OMV Petrom – Neptun Deep
- Nuclearelectrica – Cernavodă 3 and 4
- Eurostat – Hourly labour costs 2025
- European Commission – Economic forecast for Romania